This Article Answers the Following Questions
- When must a Florida HOA obtain competitive bids?
- Is an HOA board required to accept the lowest construction bid?
- Why can bids for the same HOA project differ by hundreds of thousands of dollars?
- How can a board determine whether construction bids are truly comparable?
- What does it mean to “level” construction bids?
- What should an HOA board compare besides the total price?
- How do exclusions, allowances, assumptions, and alternates affect a proposal?
- What warning signs may be hidden inside a low bid?
- How should an HOA board document its contractor-selection process?
- When should an HOA involve construction counsel or an owner’s representative?
Five Bids. A $700,000 Difference. How Does an HOA Board Choose?
It is Tuesday night.
Five construction proposals are spread across the conference table. The contractors all appear qualified. Each proposal claims to address the association’s project.
But there is a $700,000 difference between the bids.
The board members look at one another. Finally, someone asks:
“How do we know which one is right?”
That is the real problem.
The board has obtained competitive bids. But it may not have received comparable bids.
Florida Law Does Not Require the HOA to Choose the Lowest Bid
Florida law generally requires an HOA to obtain competitive bids when a contract for materials, equipment, or services exceeds 10% of the association’s total annual budget, including reserves.
However, Florida Statute § 720.3055 specifically states that an association is not required to accept the lowest bid.
That distinction matters.
The board’s responsibility is not simply to select the smallest number. It is to make an informed decision based on the project’s scope, risks, contractor qualifications, and anticipated total cost.
The association’s governing documents may also impose additional bidding or approval requirements. Those requirements should be reviewed before the board awards a substantial construction contract.
Why Can Construction Bids Be So Far Apart?
A large difference between proposals does not necessarily mean one contractor is overcharging or another is offering a bargain.
It may mean the contractors are not pricing the same work.
One proposal may include:
- Permits and inspections
- Temporary protection
- Site preparation
- Engineering coordination
- Material testing
- Debris removal
- Resident-access planning
- Landscaping restoration
- Extended warranties
- Insurance or bonding requirements
Another proposal may exclude several of those items or treat them as allowances—estimated amounts that can change after construction begins.
The base price looks lower. The association’s actual cost may not be.
The Scope May Be Creating the Confusion
Construction bids are only as reliable as the documents used to solicit them.
If contractors receive incomplete drawings, a general project description, or different information during site visits, they must make their own assumptions.
Those assumptions can produce dramatically different prices.
For example:
- One contractor may assume extensive concealed damage.
- Another may price only the damage currently visible.
- One may include full replacement.
- Another may propose limited repairs.
- One may include resident relocation or access accommodations.
- Another may assign those responsibilities to the association.
- One may include permit, engineering, and inspection costs.
- Another may exclude them entirely.
The board cannot make a meaningful price comparison until it understands those differences.
Competitive Bidding Is Not the Same as Bid Leveling
Bid leveling means organizing each proposal against the same scope, specifications, assumptions, and pricing categories.
Instead of comparing five bottom-line numbers, the board compares the proposals line by line.
A bid-leveling review may examine:
- Base scope: What work is included in the quoted price?
- Exclusions: What is specifically left out?
- Allowances: Which costs are estimates rather than fixed prices?
- Alternates: What optional work may be added or removed?
- Unit prices: How will additional quantities be priced?
- Materials: Are the contractors proposing equivalent products and systems?
- Schedule: How long will the work take?
- Phasing: How will the project affect residents and common areas?
- Change-order markups: What additional charges may apply?
- Warranties: What protection remains after completion?
- Insurance and bonding: What coverage and financial protections are included?
Once those items are organized, the reasons for a $700,000 difference may become much clearer.
The Lowest Bid May Carry the Most Uncertainty
A low proposal is not automatically a bad proposal. A high proposal is not automatically the best one.
The concern is uncertainty.
A proposal may appear inexpensive because it contains:
- A loosely defined scope
- Numerous allowances
- Significant exclusions
- Low estimated quantities
- No clear project schedule
- Vague material specifications
- Broad rights to increase pricing
- Limited responsibility for concealed conditions
- No defined change-order process
Those gaps may later become change orders, delays, payment disputes, or requests for additional assessments.
The board should evaluate what the price includes—not merely where the price falls among the other bids.
When a Low Bid Is Really a Cash-Flow Bid
Not every low bid is a warning sign. A contractor may have lower overhead, better supplier pricing, or a more efficient approach.
But sometimes a contractor bids aggressively because the company needs immediate cash flow.
The deposit or first project draw may be needed to cover payroll, suppliers, subcontractors, or obligations from an earlier project. Once that money is used, the contractor may need to secure another job—and another deposit—to keep work moving on the association’s project.
That cycle can lead to:
- Delayed material orders
- Unpaid subcontractors or suppliers
- Front-loaded payment requests
- Work slowing after the early draws are paid
- Frequent change orders used to generate additional revenue
- Crews being moved to newer projects
- Liens, delays, or project abandonment
A low price alone does not prove that a contractor has financial problems. But when one proposal is substantially lower than the others, the board should investigate whether the contractor has the financial capacity to complete the work.
For a significant project, the board should consider:
- Reviewing the proposed schedule of values and payment structure
- Avoiding deposits or early draws that are disproportionate to the work
- Requiring milestone-based payments tied to verified progress
- Collecting lien releases with each payment
- Checking the contractor’s lien, litigation, and payment history
- Evaluating whether payment and performance bonds are appropriate
The lowest bid may appear to protect the association’s budget. If the contractor cannot finance the work through completion, however, it may expose the association to substantially greater costs.
What Should the Board Do Before Voting?
Before awarding the contract, the board should slow the process down long enough to answer several important questions.
1. Confirm That Every Contractor Priced the Same Scope
The association should establish one written scope of work supported by the appropriate plans, specifications, reports, and project requirements.
If the scope changes, every bidder should receive the same written clarification.
2. Separate Fixed Pricing From Allowances
Allowances can make a proposal appear more certain than it really is.
The board should identify which amounts are fixed, which are estimates, and what will happen if the actual cost exceeds an allowance.
3. Require Written Clarification of Assumptions and Exclusions
Important explanations should not remain in a salesperson’s presentation or a board member’s notes.
If a contractor clarifies the proposal, the clarification should be documented and incorporated into the final contract.
4. Evaluate the Contractor, Not Just the Proposal
The board should consider relevant project experience, licensing, insurance, financial capacity, litigation or disciplinary history, subcontractor management, and the team that will supervise the work.
Our related guide, 10 Questions Every Condo Board Should Ask Before Hiring a Contractor, provides a broader contractor-selection checklist that can also help HOA boards evaluating major projects.
5. Compare the Likely Total Project Cost
The contract amount may be only part of the association’s financial exposure.
The board should also consider:
- Professional fees
- Testing and inspections
- Permit costs
- Contingency funds
- Resident-access expenses
- Temporary facilities
- Landscaping or property restoration
- Potential escalation
- Change-order exposure
The lowest initial bid may not produce the lowest final project cost.
6. Review the Proposed Contract Before Awarding the Work
The proposal describes what the contractor is offering.
The contract determines what happens when the project encounters a delay, disputed scope, hidden condition, payment disagreement, defective work, or termination.
Before signing, the board should understand:
- Payment requirements
- Change-order procedures
- Delay provisions
- Insurance obligations
- Indemnification language
- Warranty obligations
- Termination rights
- Dispute-resolution procedures
Contract review should occur before the association commits to a contractor—not after the project encounters a problem.
7. Document the Board’s Decision-Making Process
The association is not required to choose the lowest bid, but the board should be able to explain why it selected a particular proposal.
The record should reflect that the board considered relevant factors such as scope, qualifications, exclusions, schedule, risk, and anticipated total cost.
The strongest decision is not necessarily unanimous. It is informed and defensible.
Volunteer Boards Should Not Have to Become Construction Estimators
HOA board members are volunteers.
They may have substantial professional and business experience, but that does not necessarily prepare them to compare construction methods, interpret technical exclusions, evaluate unit pricing, or negotiate a multimillion-dollar construction contract.
The right team may include:
- An engineer or other appropriate design professional
- A qualified construction consultant
- An owner’s representative
- The association’s property manager
- Experienced construction counsel
Each professional serves a different role. Together, they can help the board understand the project before the association commits substantial funds.
The Question Is Not “Which Bid Is Cheapest?”
The better question is:
Which proposal gives the association the clearest scope, the most appropriate contractor, the strongest protections, and the most reliable understanding of the project’s likely total cost?
Five bids may satisfy a competitive-bidding requirement.
They do not automatically give the board enough information to make the right decision.
How Wyman Legal Solutions Helps HOA Boards
Wyman Legal Solutions helps Florida HOAs and condominium associations navigate significant construction projects before and after disputes arise.
We assist with substantial matters involving:
- Construction contract review and negotiation
- Proposal and contract inconsistencies
- Scope and change-order disputes
- Payment and lien issues
- Contractor performance problems
- Project delays
- Defective or incomplete work
- Major association construction conflicts
If your association is preparing to award a substantial construction contract—or the bidding process has already exposed serious scope, cost, or contractor concerns—call Wyman Legal Solutions at (561) 678-5835.